Research Project Timeline

Systematic Literature Review · Gantt Chart

21 July 2026 – 31 October 2026 · 103 days · 7 phases · 7 milestones

Today

23 Jul 2026

Task / Phase
July 2026
August 2026
September 2026
October 2026
21
22
23
24
25
26
27
28
29
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Phase 1 · Research Planning
Select Research Domain21 Jul
Finalize Research Topic22 Jul
Generate Search Keywords23 Jul–24 Jul
Generate Synonyms24 Jul–25 Jul
Create Boolean Search Strings25 Jul–26 Jul
Define Inclusion Criteria26 Jul–27 Jul
Define Exclusion Criteria27 Jul
Prepare Quality Assessment Checklist28 Jul
Select Digital Libraries29 Jul
Design Master Table30 Jul
Protocol Review31 Jul
M1 · Research Protocol Completed31 Jul
M1
Phase 2 · Literature Search
Search IEEE Xplore1 Aug–3 Aug
Search ACM Digital Library3 Aug–5 Aug
Search Springer / ScienceDirect5 Aug–8 Aug
Search Scopus / Web of Science8 Aug–10 Aug
Export Citations / Download PDFs10 Aug–12 Aug
Remove Duplicates / Organize Library12 Aug–14 Aug
M2 · Literature Collection Completed14 Aug
M2
Phase 3 · Paper Screening
Title Screening15 Aug–20 Aug
Abstract Screening21 Aug–25 Aug
Full-text Screening26 Aug–30 Aug
Finalize Selected Papers31 Aug
M3 · Selected Papers Finalized31 Aug
M3
Phase 4 · Reading & Data Extraction
Read Selected Papers1 Sep–20 Sep
Populate Master Table1 Sep–25 Sep
Quality Assessment Scoring10 Sep–25 Sep
M4 · Master Table Completed25 Sep
M4
Phase 5 · Analysis & Visualization
Publication Trend Analysis26 Sep–28 Sep
Methodology & Thematic Analysis29 Sep–2 Oct
Research Gap Identification3 Oct–5 Oct
Create Visualizations (PRISMA, Charts, Taxonomy, Heatmaps)6 Oct–10 Oct
M5 · Analysis Completed10 Oct
M5
Phase 6 · Writing
Introduction / Background11 Oct–13 Oct
Methodology14 Oct–15 Oct
Results16 Oct–19 Oct
Discussion / Future Work20 Oct–22 Oct
Conclusion / References / Formatting23 Oct–24 Oct
M6 · First Draft Completed24 Oct
M6
Phase 7 · Revision & Submission
Proofreading25 Oct–27 Oct
Supervisor Review28 Oct–30 Oct
Final Formatting / Submission31 Oct
M7 · Final Submission31 Oct
M7

Legend

✓ Completed
🔄 In Progress
⏳ Pending
◆ Milestone

Phase colors

Research Planning
Literature Search
Paper Screening
Reading & Data Extraction
Analysis & Visualization
Writing
Revision & Submission

Project summary

Duration
21 Jul – 31 Oct 2026
Total days
103
Tasks
36
Milestones
7
Completed tasks
0
In progress
0

Systematic Literature Review · Project timeline · Generated 23 July 2026